top of page
Timelne
Timeline
Please note that this timeline is subject to change and will be updated as appropriate.
2019
April 2019
Utah Legislature passes HB 411, enabling the Community Renewable Program (CRP).
December 2019
Utah Public Service Commission adopts administrative rules to enable CRP.
23 Utah communities adopt 100% by 2030 renewable energy resolutions.
2021
February 2021
Action: Distribute Governance Agreement (GA) for signature to committed communities.
July 2021
Decision: Does eligible local government sign GA and pay Phase 1 cost? Allows voting on utility program design.
2022
July 2022
Decision: Does eligible local government sign GA?
Action: Participating local governments pay Phase 2 cost.
2023
September 2023
Decision: Does participating local government sign the Utility Agreement (UA)?
Action: Submit joint program application to Utah Public Service Commission (PSC).
Decision: Execute contract for new renewable energy resources?
February 2024
Decision: Does Utah PSC approve program application? (could happen as soon as Nov. 2023)
May 2024
Decision: Does participating local government pass required ordinance within 90 days? (could happen as soon as Feb. 2024)
2024
November 2023